VES Kuyumba-Taishet Main Oil Pipeline

VES Kuyumba-Taishet Main Oil Pipeline

In order to support the utilities of main oil pipeline 'Kuyumba-Tayshet', three distribution substations 110kV/10kV will be built on site. Their total installed power capacity will be 25.6MW, as well as two chain main power transmission line 110kV which is 326km long. VELESSTROY is involved in provision of off-site power supply networks for Main Pump Station 1, Pump Station 2 and Pump Station 3 to implement the projects on turn-key basis.

Map
Quick facts
Client "TransneftElektrosetServis" construction period 2014 - 2015
Construction turn-key
Manpower - 193